Analisis Produktivitas Alat Gali Muat Menggunakan Metode Overall Equipment Effectivenees Pada Kegiatan Pengupasan Lapisan Penutup Overburden Di Blok 3 PT. Antang Gunung Meratus, Kabupaten Tapin, Provinsi Kalimantan Selatan
Abstract
As a subsidiary of PT. Baramulti Sukses Sarana (BSSR), PT. Antang Gunung Meratus is a coal
mine located in South Kalimantan, Indonesia. In 2004 the Indonesian government entered into a
joint agreement for coal mining business work (PKP2B). PT. Antang Gunung Meratus uses a
Komatsu PC 2000-8 type excavator for the overburden loading process with a productivity target
for the contractor of 860/hour per unit. The production target per unit in one month at the Warute
Pit is 549,000 BCM/month. Production on the PC 2000-8 excavator unit with unit number PC
2008-X169 was 433,062 BCM/month. analyze the productivity of the loading digging equipment
obtained using actual calculations and the Overall Equipment Effectiveness (OEE) method, as
well as analyzing the factors that influence the productivity of the Komatsu PC 2000-8 loading
digging equipment in overburden removal activities. The OEE method is used to analyze how to
improve equipment performance. include low time effective work and work efficiency and the
planned distribution time has not been achieved. Efforts that can be made to achieve production
targets include increasing effective working time by reducing the time obstacles are avoided,
optimizing tool work efficiency, training operator skills to support the circulation time of loading
and digging equipment and adding tools
References
Overall Equipment Effectiveness (OEE) di PT. Tanito Harum, Tenggarong,Kalimantan