Pengambilan Data Cycle Time Menggunakan Aplikasi Seconds Count Pada Kajian Produktivitas Alat Gali Muat PT. X
Abstract
In the productivity study, there are several things that are done to achieve maximum productivity, including observing loading patterns and cycle time recording. Cycle time recording is usually done manually with stopwatch and stationery. Recording in this way has a fairly large level of measurement error, therefore another method is needed to carry out cycle time measurement activities so as to produce more accurate circulation time calculations, one of which is with the help of the Seconds Count application.
The purpose of this study is to identify and analyze the effectiveness of using the Seconds Count application. The use of the Seconds Count application makes it easier to perform data retrieval and analysis of actual front conditions. The results of productivity calculations using data obtained from the Seconds Count application are compared with productivity calculations using Truck Count data and the largest difference is 5.27% so that the use of the Seconds Count application in the study of productivity of digging tools can be concluded to be effective.
Keywords: Seconds Count, productivity, cycle time
References
Caterpillar. 2004. Caterpillar Performance Handbook Edition 34th. CaterpillarInc. Peoria, Illinois, USA
Hartman, H. 1987. Introductory Mining Enginering. The University of Alabama. Tuscaloska Alabama.
Hustrulid, W. & Kuchta, M., (1998). Open Pit Mine Planning and Design: Vol. 1-Fundamentals. AA Balkema Netherland.
Indonesianto, Yanto. 2020. Pemindahan Tanah Mekanis. Program Studi Teknik Pertambangan, Institut Teknologi Nasional Yogyakarta. Yogyakarta.
J.A. Franklin, E. Broch dan G. Walton. 1971. Logging The Mechanical Character of Rock. Proceeding of Institution of Mining and Metallurgy.
Khair, Abdul., Triantoro, Agus., Riswan., Hidayat, Nur Wahyu. 2019. Evaluasi Pencapaian Target Produktivitas Alat Gali Muat Dan Alat Angkut Pada Aktivitas Pemindahan Overburden di Pit 1 Blok 15 PT. Rimau Energy Mining, site Putut Tawuluh, Jurnal Himasapta, Vol. 4, No. 1, pp 17 – 24.
Morgan, W. and Peterson, L. 1968. Determining Shovel-Truck Productivity, Mining Engineering, 76-80, December.
Oemiati, Nurnilam., Revisdah, Rahmawati. 2020. Analisa Produktivitas Alat Gali Muat Dan Alat Angkut Pada Pengupasan Lapisan Tanah Penutup (Overburden), Jurnal.UM-Palembang, Vol. 06, No. 03.
Projosumarto, Partanto. 1995. Pemindahan Tanah Mekanis. Departemen Tambang, Institut Teknologi Bandung. Bandung.
Prodjosumarto, Partanto. 2000. Pemindahan Tanah Mekanis. Bandung: Program Studi Teknik Pertambangan, Institut Teknologi Bandung.
Rai, Made Astawa., Suseno, Kramadibrata., dan Ridho, Kresna Wattimena. dkk. 2014. Mekanika Batuan. Penerbit ITB: Bandung
Susanto, Romadhona P, D. 2019. Kajian Teknis Produktivitas Unit Peremuk Batu Andesit di PT. Gawi Maju Karsa Kabupaten Purworejo Provinsi Jawa Tengah. Skrispi. Universitas Pembangunan Nasional Veteran Yogyakarta.
Winarno, Eddy., Inmarlinianto., Suretno Aldi. 2018. Kajian Teknis Produksi Alat Muat dan Alat Angkut pada Pengupasan Overburden Tambang Batubara di PT Mandiri Intiperkasa, Kalimantan Utara, Jurnal Teknologi Pertambangan, Vol. 4, No. 2.