PENINGKATAN PRODUKTIFITAS UNIT CRUSHING PLANT III UNTUK MENCAPAI TARGET PRODUKSI DI PT. BATU KALI WELANG AMPUH KABUPATEN PASURUAN PROVINSI JAWA TIMUR
Abstrak
Batu Kali Welang Ampuh (BKWA) Ltd is a company engaged in andesite stone mining business. The production target is planned to achieve 1000 tons/days. In fact, based on the observation of the dump truck loading and unloading as well as on the calculation of the existing equipment capability in crushing plant III unit, this company only reached the production target 364 tons/day or 121.3 ton/hour. So, in order to achieve the desired production target, a research on the crushing unit needs tobe done. Based on the observations and calculations from the field data, the condition of the usage avaibility value of mechanical devices obtained : hopper was 97.60%, vibrating feeder was 100%, jaw crusher was 92.27%, belt conveyor was 83.48%, and vibrating screen was 82.63%. In order to increase the production, there should be improvement efforts on working time. So, by the improvement of the time constrain, the effective working time improved from 177 minutes/day to 385 minutes/day or 6.42 hours/day. Thus, it will increase the production target from 364 tons/day to 1001.52 tons/day.
Referensi
Kholis Muhammad, 2012. Kajian Teknis Unit Peremuk Batu Andesit Di PT. Tirtobumi Adyatunggal Kabupaten Pasuruan, Institut Teknologi Adhi Tama Surabaya.
Partanto P 1995, Pemindahan Tanah Mekanis, Jurusan Teknik Pertambangan, Institut Teknologi Bandung
Kurimoto Ltd. Reference Book. Crushing and Screening
Taagart Arthur F (1994), Handbook of Mineral Dreshing, Wiley-Interscience Publication, New York
Wills B.A (2005), Mineral Processing Technology, 7th edition, Elsevier Ltd.
Prosiding ini memberikan akses terbuka langsung ke isinya dengan prinsip bahwa membuat penelitian tersedia secara gratis untuk publik mendukung pertukaran pengetahuan global yang lebih besar.
Semua artikel yang diterbitkan Open Access akan segera dan secara permanen gratis untuk dibaca dan diunduh semua orang.